Completed Project Highlights

Below are just a couple highlights of capital projects that have been completed with Measure A funds:

Primary ProjectSub ProjectYear Completed Total Project Cost Measure A Expenditures Grant Expenditures SACTRAK ID STA Project IDCompletion Date Per STA Capital Pivot
Local Freeway Interchange Congestion Relief Upgrades
Cosumnes Blvd. I-5 Interchange2016 85,315,164 8,588,138 31,009,376 SAC18380A10CS/A49CS2016 8,588,138
Central Galt Interchange2013 50,641,711 9,966,000 13,962,875 SAC20580A48GT2013 9,966,000
Grantline Rd. Hwy 99 Interchange Upgrade2008 77,400,000 37,229,290 - SAC20520A50EG2008 37,229,290
Sheldon Rd. Hwy 99 Interchange Upgrade2010 73,470,838 8,291,743 20,801,000 SAC19380A53EG2010 8,291,743
Watt Ave. Hwy 50 Interchange2014 38,318,000 11,835,390 26,962,680 SAC19350A54SC2014 11,835,390
Local Freeway Interchange Congestion Relief Upgrades Total 325,145,713 75,910,561 92,735,931
Local Arterial Program
Antelope Road Watt Ave to Auburn Blvd.Roseville Rd. to I-80 Phase 12009 12,397,000 1,088,744 6,200,000 SAC15030A02CH2009 1,088,744
Bradshaw Rd. Grantline Rd. to Folsom Blvd.Calvine Rd. to Florin Rd. Phase 12010 19,547,000 7,923,277 - SAC19310A07SC2010 7,923,277
Folsom Blvd: 65th St. to Sunrise Blvd.Bradshaw Rd. to Sunrise Blvd. Phase 12010 4,759,152 5,066,265 3,659,000 SAC21470A14RC2010 5,066,265
Bradshaw Rd. to Sunrise Blvd. Phase 22012 14,667,761 36,455 10,805,860 SAC24191A14RC2012 36,455
Bradshaw Rd. to Sunrise Blvd. Phase 32012 6,836,770 2,724,000 SAC24469A14RC2012
Bradshaw Rd. to Sunrise Blvd. Phase 42018 5,062,000 3,093,804 4,838,000 SAC24717A14RC2018 3,093,804
Bradshaw Rd. to Sunrise Blvd. Phase 52020 6,100,000 1,445,428 5,500,000 SAC25008A14RC2020 1,445,428
Folsom Bridge Crossing2009 145,851,098 37,577,078 100,152,288 SAC22340A15FS2009 37,577,078
Consumnes River Permanent Open Space PreserveN/A 5,000,000 5,000,000 - N/AA16JPMN/A 5,000,000
Greenback Ln. I/80 to Auburn/Folsom Rd.West City Limit to Fair Oaks Blvd.2009 19,176,000 2,225,000 16,188,000 SAC25302, part of larger project, not completedA18CH2009 2,225,000
Sunrise Blvd. Placer Co. to Grant Line Rd.Folsom Blvd to White Rock Rd 2021 7,735,000 10,948,038 - SAC25176A32RC2021 10,948,038
Sunrise Blvd. Placer Co. to Grant Line Rd.Oak Ave. to Antelope Rd. Phase 12014 5,178,000 4,528,000 650,000 SAC16920A34CH2014 4,528,000
Sunrise Blvd. Placer Co. to Grant Line Rd.Greenback Ln. to Oak Ave Phase 22016 11,850,000 600,000 5,382,800 See Email in folderA35CH2016 600,000
Local Arterial Program Total 264,159,781 79,532,089 156,099,948
Rail Transit Improvements
South Sac LRT Extension2022 270,000,000 25,265,683 240,312,246 REG15053A39RT2022 25,265,683
DNA LRT Extension2012 49,000,000 37,311,000 14,711,845 REG17320A41RT2012 37,311,000
LRT I-80 Corridor Improvements2019 247,200 247,200 - REG16470A42RT 247,200
Rail Transit Improvements Total 319,247,200 62,823,883 255,024,091
Regional Bus/Carpool Lane Connectors/Extensions
I-80 I-5 to Capital City FreewayI-80 I-5 to Capital City Freeway2017 63,259,688 722,688 62,537,000 CAL18450A44CT2017 722,688
Hwy 50 Bus/Carpool Lanes Surise Blvd. to DowntownSunrise Blvd. to Downtown Phase 12012 100,406,202 32,793,233 67,612,969 CAL16790A47CT2012 32,793,233
Regional Bus/Carpool Lane Connectors/Extensions Total 163,665,890 33,515,921 130,149,969
Grand Total 1,072,218,584 251,782,454 634,009,939 251,782,454
Completed Projects
Primary ProjectSub ProjectYear Completed Total Project Cost Measure A Expenditures Grant Expenditures SACTRAK ID STA Project IDCompletion Date Per STA Capital Pivot
Local Freeway Interchange Congestion Relief Upgrades
Cosumnes Blvd. I-5 Interchange2016 85,315,164 8,588,138 31,009,376 SAC18380A10CS/A49CS2016 8,588,138
Central Galt Interchange2013 50,641,711 9,966,000 13,962,875 SAC20580A48GT2013 9,966,000
Grantline Rd. Hwy 99 Interchange Upgrade2008 77,400,000 37,229,290 - SAC20520A50EG2008 37,229,290
Sheldon Rd. Hwy 99 Interchange Upgrade2010 73,470,838 8,291,743 20,801,000 SAC19380A53EG2010 8,291,743
Watt Ave. Hwy 50 Interchange2014 38,318,000 11,835,390 26,962,680 SAC19350A54SC2014 11,835,390
Local Freeway Interchange Congestion Relief Upgrades Total 325,145,713 75,910,561 92,735,931
Local Arterial Program
Antelope Road Watt Ave to Auburn Blvd.Roseville Rd. to I-80 Phase 12009 12,397,000 1,088,744 6,200,000 SAC15030A02CH2009 1,088,744
Bradshaw Rd. Grantline Rd. to Folsom Blvd.Calvine Rd. to Florin Rd. Phase 12010 19,547,000 7,923,277 - SAC19310A07SC2010 7,923,277
Folsom Blvd: 65th St. to Sunrise Blvd.Bradshaw Rd. to Sunrise Blvd. Phase 12010 4,759,152 5,066,265 3,659,000 SAC21470A14RC2010 5,066,265
Bradshaw Rd. to Sunrise Blvd. Phase 22012 14,667,761 36,455 10,805,860 SAC24191A14RC2012 36,455
Bradshaw Rd. to Sunrise Blvd. Phase 32012 6,836,770 2,724,000 SAC24469A14RC2012
Bradshaw Rd. to Sunrise Blvd. Phase 42018 5,062,000 3,093,804 4,838,000 SAC24717A14RC2018 3,093,804
Bradshaw Rd. to Sunrise Blvd. Phase 52020 6,100,000 1,445,428 5,500,000 SAC25008A14RC2020 1,445,428
Folsom Bridge Crossing2009 145,851,098 37,577,078 100,152,288 SAC22340A15FS2009 37,577,078
Consumnes River Permanent Open Space PreserveN/A 5,000,000 5,000,000 - N/AA16JPMN/A 5,000,000
Greenback Ln. I/80 to Auburn/Folsom Rd.West City Limit to Fair Oaks Blvd.2009 19,176,000 2,225,000 16,188,000 SAC25302, part of larger project, not completedA18CH2009 2,225,000
Sunrise Blvd. Placer Co. to Grant Line Rd.Folsom Blvd to White Rock Rd 2021 7,735,000 10,948,038 - SAC25176A32RC2021 10,948,038
Sunrise Blvd. Placer Co. to Grant Line Rd.Oak Ave. to Antelope Rd. Phase 12014 5,178,000 4,528,000 650,000 SAC16920A34CH2014 4,528,000
Sunrise Blvd. Placer Co. to Grant Line Rd.Greenback Ln. to Oak Ave Phase 22016 11,850,000 600,000 5,382,800 See Email in folderA35CH2016 600,000
Local Arterial Program Total 264,159,781 79,532,089 156,099,948
Rail Transit Improvements
South Sac LRT Extension2022 270,000,000 25,265,683 240,312,246 REG15053A39RT2022 25,265,683
DNA LRT Extension2012 49,000,000 37,311,000 14,711,845 REG17320A41RT2012 37,311,000
LRT I-80 Corridor Improvements2019 247,200 247,200 - REG16470A42RT 247,200
Rail Transit Improvements Total 319,247,200 62,823,883 255,024,091
Regional Bus/Carpool Lane Connectors/Extensions
I-80 I-5 to Capital City FreewayI-80 I-5 to Capital City Freeway2017 63,259,688 722,688 62,537,000 CAL18450A44CT2017 722,688
Hwy 50 Bus/Carpool Lanes Surise Blvd. to DowntownSunrise Blvd. to Downtown Phase 12012 100,406,202 32,793,233 67,612,969 CAL16790A47CT2012 32,793,233
Regional Bus/Carpool Lane Connectors/Extensions Total 163,665,890 33,515,921 130,149,969
Grand Total 1,072,218,584 251,782,454 634,009,939 251,782,454